The City of Emporia is set to commence the Southeast Transmission Main Waterline Improvements Project in the week of June 10, 2025. This significant infrastructure endeavor aims to enhance water service reliability and accommodate future growth in the southeastern region of the city.
Project Overview
The Southeast Transmission Main Waterline Improvements Project encompasses the installation of over 24,000 linear feet of new water mains, ranging from 4-inch to 20-inch diameters.
Additionally, the project includes the addition of 223 new service lines and associated appurtenances. Construction is anticipated to continue through fall 2026, subject to weather conditions.
This initiative is a continuation of Emporia’s commitment to modernizing its water infrastructure, following the near completion of the 24th Avenue and Prairie Street Waterline Project, which involved approximately 12,600 linear feet of new water mains and 33 new service lines.
Project Details
Project Component | Details |
---|---|
Start Date | Week of June 10, 2025 |
Estimated Completion | Fall 2026 (weather permitting) |
Total Length | Over 24,000 linear feet |
Pipe Sizes | 4-inch to 20-inch diameters |
New Service Lines | 223 |
Total Project Cost | Approximately $21 million |
Contractor | Nowak Construction Company of Goddard |
Engineering Consultant | BG Consultants |
Funding Source | Kansas Department of Health and Environment Loan |
Financial Aspects
The total cost of the Southeast Transmission Main Waterline Improvements Project is estimated at $21 million, an increase from the initial projection of $15 million. The escalation is attributed to inflation and the impact of federal tariffs.
To finance the project, the Emporia City Commission approved an additional $10 million, utilizing state revolving loan funds from the Kansas Department of Health and Environment. The loan carries a favorable interest rate of 2.5%, which is below the current inflation rate.
The project is divided into phases, with the final phase extending from 12th and Garfield to the water tower near South and Carter. This phase is crucial for enhancing water service to major employers and reducing the frequency of water main breaks by an estimated 25%.
Traffic and Safety Considerations
Residents and commuters are advised to exercise caution in construction zones, adhere to posted traffic control measures, and consider alternative routes when possible.
For real-time updates on traffic and utility changes during the project, individuals can download the MyAlerts app or visit the City of Emporia Live Map.
Contact Information
For inquiries or further information regarding the Southeast Transmission Main Waterline Improvements Project, please contact the City of Emporia Engineering Department:
- Phone: 620-343-4260
- Email: eng@emporiaks.gov
- Office Hours: Monday through Friday, 8:00 a.m. to 5:00 p.m.
The Southeast Transmission Main Waterline Improvements Project represents a significant investment in Emporia’s infrastructure, aiming to provide long-term benefits to residents and businesses alike.
Through careful planning and execution, the city seeks to ensure a reliable and efficient water supply system that meets current needs and accommodates future development.